Timescales and Milestones
The exact time frame for each project will be different. How long it takes depends on various factors, such as the classification of the land, the availability of utility supplies and adequate access and whether your licence listed any impediments or conditions you need to comply with.
But all things being equal, the determining factors will depend on the size, complexity and whether you intend to intervene or participate in the construction process. So, assuming you have the licence in hand, these are the basic timescales and milestones from start to finish for a family home:
– Design and specification process: about 4 months
– Audit and Value engineering strategy: 1 month
– Bidding and contracting process: 2 months
– Ramp up period for constructor mobilisation and site security: 1 month
– Construction: allow for 14 months.
– Snagging, licensing, utilities, activation, moving in: 2 months
This is a total of 24 months, or two years. However, some of these activities can be run in parallel and others can be shortened. But in the planning stage, it’s better to allocate more time than you need, rather than have your team rushing to complete things to an unrealistic deadline, as this is where mistakes can be made as items can be overlooked, causing extra costs and time to complete.